New School Building Phase 3 – Windows & Doors

Our New School Building - Phase 3

Update 24 April 2026

With God’s help we have now also been able to fit windows and a door in our big new main building with 4 classrooms. So it is now protected from the rainy season and from burglars.

All that’s missing now are the floors and possibly plastering the inside walls.

Update 16 November 2025

The last row of bricks has been finished, and now we have been able to pour the concrete ring beam. This is the concrete ring right at the top that holds every building together (ours too). A very important step in the construction before the roof goes on.

By the way, the building is 163 square metres.

Update 20 December 2025

The roof is finished! YEAH, we did it – hard to believe, but it’s on.

Everyone is so happy!